Project justification

The Rehabilitation of the National Road EN-240, located in the Province of Cuanza Sul, Republic of Angola, runs between the locations of Cariango and Mussende, with a total length of 33 km. The importance of intervening in this road, which was previously a land road, results from the need to provide safe traffic conditions that take into consideration the increase in road traffic associated with the economic development of the country and guarantee the permanent use of this road even during the rainy season.

Scope of Works

The scope of work performed was:

  • Rehabilitation of 33 km of road between the towns of Cariango and Mussende with asphalt wearing course.
  • Construction of three bridges, one over the Fuique River (20 metres), one over the Ngango River (66 metres) and one over the Loue River (12 metres).
  • Auxiliary services such as clearing, surface drainage, horizontal and vertical signalling, and environmental recovery were also part of the scope of the project.
Sustainability

The road between the cities of Cariango and Mussende was developed in line with the IFC Environmental and Social Performance Standards. Several socio-environmental actions were developed prioritizing the education and the improvement of the quality of life of the surrounding community, such as: painting of schools, toy delivery, promotion of children’s visits to the construction site, celebration of World Environment Day, tree planting, stimulating scientific conferences, and provision of road safety education.

For more information about the Project,
get in touch through our Contact Us page.

Scroll to Top

Third Party Risk Management

Our Third-Party Risk Management System is designed to act preventively in identifying third parties and managing associated risks. It is an electronic, automated, and parameterised system integrated into our payment platform, enabling almost instantaneous screening of the reputational and financial aspects of third parties at the contracting stage. In this way, we support the procurement area in identifying the best suppliers in the market—those who share QGMI’s commitment to quality and social responsibility—while reducing our exposure to third-party risk. Our decentralised due diligence process allows the organisation to operate with confidence in the markets where it is present. 

Waste Management

We manage waste in an integrated manner by separating it, processing it through composting, and evaluating its flows. The compost produced is reused in reforestation projects.

GPS Control System

This control system enables operators to level and move earth with greater precision and speed, resulting in increased productivity, lower operating costs, and high-quality results.

SAE (Electronic Monitoring System)

Developed by our IT team, the SAE monitors the activities and working hours of both personnel and equipment in real time, reducing the time required to access performance indicators. It includes an application that reads QR codes assigned to equipment and staff and works even when no network is available. Benefits include improved cost management, enhanced productivity control, and a positive contribution to environmental sustainability.

QGMI Corporate
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.